E-Mail ALSPO D/12; Direct Access/Image Now Data Center Relocation

$
0
0

E-Mail ALSPO message D/12 announces service interruptions and outages that are anticipated to occur when the contract data center relocates the servers housing the Direct Access I, Direct Access II, Retired Global Pay and Image Now (EIPDR) databases and applications.

The following timeline is provided to assist in planning for this transition:

  • Thursday, 31 May - Direct Access and HR Imaging will be taken offline at 1700 (EST).
  • Monday, 04 June - Direct Access will be available in a reduced capacity (no self-service access). The imaging system will not be available.
  • Friday, 08 June - Direct Access will be taken offline.
  • Friday, 15 June - Direct Access and HR Imaging are both back on line in regular production environments.
  • Tuesday, 19 June - Data entry cutoff for 29 June payday.
  • Wednesday, 20 June - June end-month payday compute cycle runs.

Please see E-Mail ALSPO D/12; Direct Access/Image Now Data Center RelocationPDF file for more information.